據10月7日Neftegaz.RU.報道,烏茲別克斯坦國家石油天然氣公司(Uzbekneftegaz)的Buzakhur凝析氣田,一個初級天然氣處理裝置在短時間內建成并投入使用。
這個項目是根據烏國油董事會主席的指示和倡議執行的,目的是增加油田的油氣產量以及消除天然氣管道的水力阻力。此外,還確保了將天然氣輸送至Shurtan head設施,以處理從油井中提取的天然氣,以及天然氣輸送系統的穩定運行,可以利用現有的資源來降低項目的成本。
值得一提的是,裝置所需的分離器和通風機等均來自Mubarek天然氣處理廠。當然,在設備施工過程中還涉及到2個未使用的儲罐、不同尺寸的管道、球閥和閥門等設備。施工安裝工作由Shurtan 油氣生產基建部門執行。
由于烏茲別克斯坦國家天然氣管理局合格的專家和員工以及管理人員的高效工作,保障了初級氣體處理裝置在最短的時間內在Buzakhur油田建成并投入使用。
該項目投產后,由于天然氣供應系統管道阻力減小,Buzakhur油田的天然氣產量將增加20萬立方米/天。Buzakhur油田位于Kashkadarya地區,于2001年投入使用。
王佳晶 摘譯自 Neftegaz.RU.
原文如下:
Uzbekneftegaz: Primary gas treatment unit built and put into operation at Buzakhur field
According to UzDaily, at the Buzakhur gas condensate field of the Shurtan Oil & Gas Production Department of Uzbekneftegaz, a primary gas treatment unit was built and put into operation in a short time.
This project was implemented on the instructions and initiative of the Chairman of the Board of Uzbekneftegaz in order to increase the volume of hydrocarbon production at the field and eliminate hydraulic resistance in gas pipelines.
In addition, delivery to the Shurtan head facility for processing natural gas extracted from wells was ensured, as well as stable operation of the gas transmission system. Available internal resources were used to reduce the costs of the project.
In particular, the separator, liquid separator and ventilator required for the installation were brought from the Mubarek gas processing plant. During the construction of the device, 2 unused tanks, pipes of different sizes, ball valves and valves of the Shurtan Oil & Gas Production Department were also involved.
Construction and installation works were fully performed by the capital construction department of the Shurtan Oil & Gas Production Department.
Thanks to the efficient work of qualified specialists and employees of Uzbekneftegaz and management, a primary gas treatment device was built and put into operation at the Buzakhur field in the shortest possible time.
As a result of the launch, natural gas production from the fields of the Buzakhur group was increased by 200 thousand cubic meters per day due to a decrease in resistance in the pipelines of the gas supply system. The Buzakhur field is located in Kashkadarya region and was commissioned in 2001.