亚洲综合在线视频-亚洲综合在线观看视频-亚洲综合视频网-亚洲综合色秘密影院秘密影院-日本三区四区免费高清不卡

當前位置:全球化工設備網 > 資訊 > 行業動態 > 正文

立陶宛確認700兆瓦海上風電場選址

作者: 2020年06月30日 來源:互聯網 瀏覽量:
字號:T | T
計劃用于風力渦輪機的波羅的海近海區域距離海岸29公里,面積達137.5平方公里。場地平均水深35米,平均風速約9米/秒。

據離岸工程網站6月26日消息 立陶宛政府正加緊計劃在波羅的海開發一個700兆瓦的海上風電場,并于本周提出了該項目的選址,預計將于2030年完工。

計劃用于風力渦輪機的波羅的海近海區域距離海岸29公里,面積達137.5平方公里。場地平均水深35米,平均風速約9米/秒。

波羅的海風力渦輪機的投資者將通過招標方式進行選擇。計劃于2023年2月1日組織在海洋地區開發和運營這些發電廠的投標。

能源部長?ygimantas Vai?iūnas表示:“通過使用海上風電,我們將實現雄心勃勃的可再生能源目標,并減少從其他國家的電力進口。我們的目標是以最有效和最具競爭力的方式開發海上風電,這也將是吸引世界級投資者投資立陶宛能源的機會。”

政府表示:“波羅的海一個這樣的風力發電場每年可發電約2.5-3太瓦時,這幾乎是立陶宛目前電力需求的四分之一。據估計,這一容量的風電場將吸引多達10億歐元的私人投資。”

考慮到其他國家的經驗以及在海洋領土上建立連接計劃中的渦輪機的網絡可能需要八年的時間,政府還建議輸電系統運營商開始準備將計劃開發的渦輪機連接至電網。

吳恒磊 編譯自 離岸工程

原文如下:

Lithuania Selects Location for 700MW Offshore Wind Farm

The government of Lithuania is pressing ahead with plans to develop a 700MW offshore wind farm in the Baltic Sea, and has this week proposed a location for the project which is expected to be completed by 2030.

The offshore area in the Baltic Sea planned for the wind turbines is located 29 kilometers from shore and covers an area of 137.5 km2. The average water depth at the site is 35 meters, and the average wind speed is approximately 9 m/s.

Investors in the wind turbines in the Baltic Sea will be selected by tender. The tenders for the development and operation of these power plants in the marine territory are planned to be organized on February 1, 2023.

“By employing offshore wind, we will achieve our ambitious renewable energy targets and reduce electricity imports from other countries. Our goal is to develop offshore wind in the most efficient and competitive way, and this will also be an opportunity to attract world-class investors to Lithuanian energy,” says Minister of Energy ?ygimantas Vai?iūnas.

"A wind farm of this capacity in the Baltic Sea can produce approximately 2.5-3 TWh of electricity per year, which is nearly a quarter of Lithuania’s current electricity demand. It is estimated that wind farms of this capacity will pull in as much as EUR 1 billion in private investments," the government said.

Taking into account the experience of other countries and the fact that the development of networks in the marine territory for connecting the planned turbines may take up to eight years, the Government additionally suggested that the transmission system operator begin preparatory work for connecting the turbines that are planned to be developed to the power grids, the government said.

全球化工設備網(http://www.tupvw34.cn )友情提醒,轉載請務必注明來源:全球化工設備網!違者必究.

標簽:立陶宛 海上風電場 風力渦輪機

分享到:
免責聲明:1、本文系本網編輯轉載或者作者自行發布,本網發布文章的目的在于傳遞更多信息給訪問者,并不代表本網贊同其觀點,同時本網亦不對文章內容的真實性負責。
2、如涉及作品內容、版權和其它問題,請在30日內與本網聯系,我們將在第一時間作出適當處理!有關作品版權事宜請聯系:+86-571-88970062